Category: Kitchen

Painful Errors

20 June 202311 February 2024 gjj

Because I am taking a relaxed approach and only visiting on occasion and not daily, errors begin to occur. When I arrived today I was upset to see what looks to be cement used as ....

Continue reading
Entrance Gates and Arch, External, Kitchen, Utility

Windows 1

16 June 202311 February 2024 gjj

As I am taking a more relaxed approach at the moment I did not arrive until nearly midday to find that the wall had been finished. cleaned and tiled. Henri will, be happy as it ....

Continue reading
External, Garden, Kitchen, Utility, Windows

Concrete Floor Goes In

13 June 202311 February 2024 gjj

When I arrived on site it was about an hour before the concrete was due to arrive and I found four builders busy on the separation wall which, in a morning, they had just about ....

Continue reading
Entrance Gates and Arch, External, Kitchen, Lounge, Utility

PV Panels And Another Cable

2 June 202311 February 2024 gjj

After pouring the concrete for the lintel above the door, the team got back to floor preparation laying the reinforcing bar for the concrete pour. We wanted to organise it for this week but the ....

Continue reading
Car Park, Entrance Gates and Arch, External, Kitchen, Lounge, Utility

More Floor and Lintels

1 June 202311 February 2024 gjj

Yesterday we had a visit from the windows supplier to agree the height of the lintels above the new door in the utility room and for the existing windows. Florent can now get on with ....

Continue reading
Kitchen, Lounge, Utility

Electrics and External Progress

26 May 202311 February 2024 gjj

The temporary barrier between our garden and Henri's has been taken down in preparation for laying the foundations of the wall that has to be built there. So for a while the dogs cannot be ....

Continue reading
BBQ/Workshop, Car Park, Entrance Gates and Arch, External, Garden, Kitchen, Lounge, Utility

Tie bar and Internal Services

25 May 202311 February 2024 gjj

The tie bar arrived late last night and when I arrived this morning it had already been positioned. I helped with the tensioning but essentially it is done and the remaining wall can be taken ....

Continue reading
Car Park, External, Kitchen, Utility

BBQ and Services

22 May 202311 February 2024 gjj

When I arrived this morning after leaving early on Friday I was pleased to find the BBQ and Workshop area had been prepared and compacted along with the cleanse and preparation of the bike store. ....

Continue reading
BBQ/Workshop, Bike Store, Entrance Gates and Arch, External, Garden, Kitchen, Lounge, Utility

Internal Breakout

19 May 202311 February 2024 gjj

With the pathway down to the house, The contractors concentrated on breaking out and levelling the internal floor and removing the internal wall. They did not take it all down as there was concern about ....

Continue reading
Kitchen, Lounge, Utility

Floor Removal and Tidying Up

14 May 202311 February 2024 gjj

Tea time over I took these high level shots to show the trenches all filled. Philippe and I then turned our attention to removing the rest of the first floor (or at least the bits ....

Continue reading
Car Park, Entrance Gates and Arch, External, Garden, Guest Bedroom, Kitchen, Lounge, Lower Mezzanine, Master Bedroom, Upper Mezzanine, Utility

Posts navigation

Older posts
Newer posts

Recent Posts

  • August 2
  • July 31
  • July 25
  • July 24
  • July 23

Archives

Categories

Proudly powered by WordPress | Theme: news-box by wpthemespace.com.