15 rue Sainte Benête – The Development Blog

15 rue Sainte Benête – The Development Blog

Latest News
Welcome (Sticky Post)  |  
May 19  |  
May 16  |  
May 15  |  
May 14  |  
May 10  |  

Category: Bike Store

Bike store at the front of the house

External Slabs 7

30 June 202415 August 2024 gjj

It's Sunday and I am back again as the tilers insist on working the weekend and I want to oversee what they are doing. Front patio BBQ/Workshop (almost finished) Front bike store. Preparing the rear ....

Continue reading
BBQ/Workshop, Bike Store, External, Garden Store

Clearing and Bits And Bobs

20 June 202425 June 2024 gjj

Emptied more shelving in the bike store and dismantled and rebuilt it in the workshop. The bike store is now clear and ready for floor slabs. Then did the same in the garden store but ....

Continue reading
BBQ/Workshop, Bike Store, Garden, Garden Store

Workshop Window and First Floor Flooring 5

6 May 202423 June 2024 gjj

Today Florent and his team are back on site for a couple of days to sort out some minor snagging issues. So I have got them to help me fit the large fixed window in ....

Continue reading
BBQ/Workshop, Bike Store, Entrance Gates and Arch, First Floor, Windows

Upper Mezzanine Floor 6

14 March 202422 June 2024 gjj

Time to move inside and make a start on the floor for the office on the upper mezzanine. First I had to finish securing the oak strengthening beams using the M12 threaded bar. Outside I ....

Continue reading
Bike Store, Garden, Garden Store, Upper Mezzanine

More Fencing and Floorboards

31 October 202311 February 2024 gjj

Dancing posts and gate cemented in. Lead flashing on storage roofs and the final joists are fitted.

Continue reading
Attic, Bike Store, External, First Floor, Garden

Windows 5 (Cills)

16 September 202311 February 2024 gjj

With the jointing finished and the embedded bush root finally dead, we were able to cut out the exposed section, drill it and fill it with more herbicide just in case and finish off the ....

Continue reading
Bike Store, External, Windows

Storage

24 August 202311 February 2024 gjj

At the moment there is just me and Esteban on site as everyone else is on holiday. Progress has slowed but not stopped. The tiles have been set on the two stores and the bike ....

Continue reading
BBQ/Workshop, Bike Store, Garden Store

Garden Stores

21 August 202311 February 2024 gjj

Esteban has started to roof the two stores. Exterior and interior views of the rear store for the garden and the front store for the bikes.

Continue reading
Bike Store, External, Garden Store

Jointing and Joists 2

19 August 202311 February 2024 gjj

More progress on the small stores which are almost ready for roofing. They have also moved onto the rear wall which is exciting. The window detail shows we are planning to leave the raw concrete ....

Continue reading
Attic, BBQ/Workshop, Bike Store, External, Garden Store

Jointing and Joists 1

17 August 202311 February 2024 gjj

After our trip to Sancerre I returned to find that the entire end wall had been jointed and the two stores virtually finished. Looking good. The slightly darker mortar helps the stones to stand out ....

Continue reading
Attic, BBQ/Workshop, Bike Store, Garden Store