August 2
The first washing machine (which will eventually end up in the coldstore) is temporarily installed. 30 years old but the Miele is still working well. Time has come for me to mark out and cut ....
Master bedroom including the en-suite and dressing areas
The first washing machine (which will eventually end up in the coldstore) is temporarily installed. 30 years old but the Miele is still working well. Time has come for me to mark out and cut ....
Lee has now applied a second coat to most of the surfaces. One final one to go then it is sanding prior to painting. The proper bandstand has arrived which is far more secure. With ....
Lee has progressed well even through he is on his own. I occupied myself by building and fitting the wardrobe units for the mezzanine space. The right had sifde was a little tight but I ....
With the insulation in place the cabling can be prepared. Took some time as the original design would not work with the positions of the ceiling support bars but eventually I found a spacing that ....
Into the master bedroom. First is the insulation. It is hot and sweaty and I am wearing a full face mask to avoid inhaling the dust so not a pleasant job.
Before fitting the ceiling plasterboard I have to prepare the cabling for the lights and also for the fans. in addition I have to get the fans out to an external point to ventilate the ....
Insulation of most the walls now done and the new corner has been boarded. I need to collect some more insulation tomorrow morning.
With no insulation or vapour barrier I am trying to use my time effectively so the IKEA cabinets have started to be assembled for the utility room. Upstairs I have completed the master bedroom internal ....
The Master bedroom radiators finally installed and tested. I cannot test the Guest Bedroom yet as the circuit includes the towel rail in the bathroom that is not fitted so I have ordered some blanking ....