May 15
The Master bedroom radiators finally installed and tested. I cannot test the Guest Bedroom yet as the circuit includes the towel rail in the bathroom that is not fitted so I have ordered some blanking ....
Guest bedroom including the en-suite area
The Master bedroom radiators finally installed and tested. I cannot test the Guest Bedroom yet as the circuit includes the towel rail in the bathroom that is not fitted so I have ordered some blanking ....
The last few days have been bank holidays or other distractions and next week I have to take a couple of days off to take Luc to the vet and me for a Covid injection ....
The plasterers have left and they did not complete the painting to the floor as there is eventually going to be a skirting board or it will be behind kitchen cabinets or other furniture. However, ....
With the concrete removed from the walls the team got on with applying a cost of lime based mortar. Not quite finished but it make a huge impact on the inside to have the walls ....
Tea time over I took these high level shots to show the trenches all filled. Philippe and I then turned our attention to removing the rest of the first floor (or at least the bits ....
Sunday was a full day working with la Métairie to finally clear the upper floor. All gone at last. Just a quick sweep to finish off.
Thanks to the generosity of our builder, I have been able to organise a week of moving hay for La Métairie with their volunteers. Because of Mike's (Baker) birthday bash I have had to spread ....
Back to emptying the hay and straw from upstairs while waiting for another windows quotation company to arrive. Although most of the straw is loose, some remains in bales and today I concentrated on getting ....