Car Park Services 1
I am using some of the oak I cut that was not used to support the electrical panel in the car park. Stephane is coming tomorrow to redo the plumbing so I have taken it ....
I am using some of the oak I cut that was not used to support the electrical panel in the car park. Stephane is coming tomorrow to redo the plumbing so I have taken it ....
While my two assistants watched on, I rearranged the main staircase components, moving them from the first floor to the upper mezzanine. I also sorted the various lengths of parquet ready for the next few ....
The first of the heating loops is installed. I took some measures as it is close to where a future enclosure in the bathroom is going to go. Having said that it will be covered ....
Before the floor can be done I need to remove the scaffolding we have been using for the upper mezzanine. However, before removing them I need to finish preparing the beams for the oak flooring. ....
I have finished cabling the panels on the car park roof and today the underfloor heating pipe is finally on site. All 500m of it. Should have been done before they fitted the heat pump ....
As part of the recording of the inverters and to make life easier for the installers I have numbered all of them with reference to the panel layout map. Soon after I had finished the ....
To enable the electrical earth to be tested, each of the three earthing points I have installed needs a breaker fitted. This allows the earth to be disconnected and tested then reconnected and tested to ....
It does not looks much but it took most of the day to fit the 16mm cabling in the distribution board then make the final connection at the temporary supply. 16mm is difficult to work ....
Back to the distribution board. The back for the main isolating switch has arrived and (I thought) it would be a five minute job to fit it in. Wrong! Working with 16mm cable is not ....