First Floor Flooring 9, EV Charger installed
A record of the position of the central point of the fibre optic cable where the rods were brought together. Now all buried and without the inspection chamber that is now redundant. On the first ....
A record of the position of the central point of the fibre optic cable where the rods were brought together. Now all buried and without the inspection chamber that is now redundant. On the first ....
The free.com engineer is due this afternoon so I spent this morning with some small issues. First, I have installed a threshold for the workshop door as there will be different tiling inside the workshop ....
No photos today. Just me and Phillipe our neighbour on site pulling through fibre rods in preparation for the visit next week of free.com to install the fibre optique cables. It has been a long ....
The finished repair of the front arch. Some changes to the kerbstones. The heat pump position had to be changed (the base was extended some time ago for it) so the pathway became too narrow ....
While I got on with finishing my panelling in the car park, Stephane sorted the incoming main and fitted a tap in the BBQ area. With the panelling all up I was able to refit ....
Back to the distribution board. The back for the main isolating switch has arrived and (I thought) it would be a five minute job to fit it in. Wrong! Working with 16mm cable is not ....