Final Floor Beams 2
The concrete base has gone into the garden store. And the new replacement beam has been installed over the existing one that gave me concerns at one end. Also te high level beam is in ....
Garden store at the back of the house
The concrete base has gone into the garden store. And the new replacement beam has been installed over the existing one that gave me concerns at one end. Also te high level beam is in ....
At the moment there is just me and Esteban on site as everyone else is on holiday. Progress has slowed but not stopped. The tiles have been set on the two stores and the bike ....
Esteban has started to roof the two stores. Exterior and interior views of the rear store for the garden and the front store for the bikes.
More progress on the small stores which are almost ready for roofing. They have also moved onto the rear wall which is exciting. The window detail shows we are planning to leave the raw concrete ....
After our trip to Sancerre I returned to find that the entire end wall had been jointed and the two stores virtually finished. Looking good. The slightly darker mortar helps the stones to stand out ....
Where the walls have been cleaned, joints chiselled and jet washed, the team can at last start filling them with the chosen colour mortar. We are using a premixed coloured mortar to give consistency over ....
I need to lift a lot of materials to the upper floors so I have bought and installed an electric hoist identical to the one I had at Le Chai. Making a start on the ....
The wall rendering is finished. The concrete support is re-shuttered to be raised to the new height. The hole to receive the far end of the new beam has been raised and moved to get ....
15 rue Sainte BenĂȘte 17770 MIGRON So this is the new property. Photos taken on our second visit to the site after our offer had been accepted. It is an enclosed site, mainly walled with ....