Attic Floor and Garden Store
Arrived late today and used the morning that remained to move some storage shelves and garden items from the rented storage to the new garden store. Lots of space in both stores now so more ....
Arrived late today and used the morning that remained to move some storage shelves and garden items from the rented storage to the new garden store. Lots of space in both stores now so more ....
to maintain the flooring for the window installation I had to lift the temporary floor I had fitted (22mm) that is the attic floor and replace it with thinner (12mm) boarding that is destined for ....
Dancing posts and gate cemented in. Lead flashing on storage roofs and the final joists are fitted.
More work on the attic floor joists while externally the ground is flattened and the pathway foundation rubble laid.
With the old warped beams removed from the upper mezzanine, a support beam to level the new oak beams is placed in position. With the first floor and lower mezzanine joists in place I have ....
The concrete base has gone into the garden store. And the new replacement beam has been installed over the existing one that gave me concerns at one end. Also te high level beam is in ....
To start the day I finished off the few remaining noggins for the mid section of the attic floor before turning my attention to the car park pergola. The concrete pads were not in quite ....
Florent's team of workers have left for the moment as we are waiting on information for the sewage treatment plant before continuing so I am on site alone. I have finished the last part of ....
What a miserable day! Almost non-stop rain during the morning which flooded the site making it difficult to do the concreting of the bases for the pergola posts for the car park. In the brief ....
Finally the jointing is finished. Scaffold down at the front to reveal its new face and the internal wall also cleared (although still a bit damp as it is inside). The top of the attic ....