Skip to content
  • 03:49
  • Wednesday
  • 2 July 2025
  • Home
  • Welcome
  • A New Project
  • Drawings
  • 15 Rue Sainte Benête Videos 28th march 2025
  • M-B Importation
15 rue Sainte Benête – The Development Blog

15 rue Sainte Benête – The Development Blog

Latest News
Welcome (Sticky Post)  |  
June 28  |  
June 27  |  
June 25  |  
June 24  |  
June 19  |  
Master Bedroom En Suite

June 28

Full story
Master Bedroom En Suite

June 27

Full story
Guest Bedroom

June 25

Full story

Windows and Timber Frame Installation 8

6 February 202411 February 2024 gjj

First thing this morning was a meeting on resolving the issues with the windows with Julien Cogné. The solutions look to be OK but the rear opening in the lounge cannot be changed. We will ....

Continue reading
Timber Frame

Staircase 4

5 February 202411 February 2024 gjj

In order to work on the upper mezzanine floor and bannisters, I decided to fit the smaller staircase between the two mezzanines. I have dismantled it downstairs and taken all the steps home for Jude ....

Continue reading
Staircase

Internal Electrics

2 February 202411 February 2024 gjj

It does not looks much but it took most of the day to fit the 16mm cabling in the distribution board then make the final connection at the temporary supply. 16mm is difficult to work ....

Continue reading
Electrics, External, Ground Floor

Timber Frame Cladding Arrives

1 February 202411 February 2024 gjj

Sitting happily at home catching up with paperwork I got an urgent call from my neighbor Andrew. Apparently a lorry had arrived from Estonia with no notice containing our timber cladding of charred and oiled ....

Continue reading
External, Timber Frame

Attic Floor and Garden Store

31 January 202411 February 2024 gjj

Arrived late today and used the morning that remained to move some storage shelves and garden items from the rented storage to the new garden store. Lots of space in both stores now so more ....

Continue reading
Attic, Garden Store

Tidying Up

30 January 202411 February 2024 gjj

Excellent weather for opening the doors and tidying up the interior before offloading the latest timber delivery. Florent has once again organised the purchase and lent me his lorry to bring it to site. Esteban ....

Continue reading
Car Park, External, Ground Floor, Staircase

Earthing

29 January 202411 February 2024 gjj

French electrical installations rely on local earthing points. With three main panels (house, PV panels on BBQ and PV panels on car park where the mains supply enters the property) I decided to fit three ....

Continue reading
BBQ/Workshop

Staircase 3

26 January 202411 February 2024 gjj

As the staircases are prefabricated, the risers are not set to match the difference between the finished floor levels (FFL). So to set the best first and last rises I have put the smaller staircase ....

Continue reading
Staircase

Staircase 2

23 January 202411 February 2024 gjj

We opted for an industrial staircase from Tecrostar in Spain. Our neighbours in Preroux have built a mezzanine and staircase from the same company and we thought it would fit well with the windows and ....

Continue reading
Staircase

Electrical Distribution Panel 2

23 January 202411 February 2024 gjj

Back to the distribution board. The back for the main isolating switch has arrived and (I thought) it would be a five minute job to fit it in. Wrong! Working with 16mm cable is not ....

Continue reading
Services

Posts pagination

Previous page Page 1 … Page 27 Page 28 Page 29 … Page 45 Next page

Recent Posts

  • June 28
  • June 27
  • June 25
  • June 24
  • June 19

Archives

Categories

Proudly powered by WordPress | Theme: news-box by wpthemespace.com.