First Floor Flooring 9, EV Charger installed
A record of the position of the central point of the fibre optic cable where the rods were brought together. Now all buried and without the inspection chamber that is now redundant. On the first ....
A record of the position of the central point of the fibre optic cable where the rods were brought together. Now all buried and without the inspection chamber that is now redundant. On the first ....
The free.com engineer is due this afternoon so I spent this morning with some small issues. First, I have installed a threshold for the workshop door as there will be different tiling inside the workshop ....
No photos today. Just me and Phillipe our neighbour on site pulling through fibre rods in preparation for the visit next week of free.com to install the fibre optique cables. It has been a long ....
The finished repair of the front arch. Some changes to the kerbstones. The heat pump position had to be changed (the base was extended some time ago for it) so the pathway became too narrow ....
Before encasing it in concrete, it is always a good idea to pressure test it for any leaks. (It passed).
The last item to remove from the house is the old stairs from our old property that I have been using to get up to the first floor with. With the floor clear I can ....
The plug has arrived so I have wired up the charger properly to feed back to the board. Only to find it is the wrong plug!
I am pressing on with the heating as the floor screeners are due soon and this must be finished for them. In order to avoid moving the (heavy) roll of tubing all the time I ....
Back indoors and downstairs to fit the next loop in the heating. This time it is the kitchen, avoiding not just the walls but also the future units including the island un unit. Working with ....
While I got on with finishing my panelling in the car park, Stephane sorted the incoming main and fitted a tap in the BBQ area. With the panelling all up I was able to refit ....