Car Park 4
Took me most of the day drilling the bottom of the 6 wooden posts and fitting the other half of the feet so that the posts could be installed to the bases. I laid the ....
Took me most of the day drilling the bottom of the 6 wooden posts and fitting the other half of the feet so that the posts could be installed to the bases. I laid the ....
To start the day I finished off the few remaining noggins for the mid section of the attic floor before turning my attention to the car park pergola. The concrete pads were not in quite ....
The inverters for the photovoltaic panels need to be fixed to the rails on which the panels sit to protect them from the weather. The fittings they sent originally were not correct and they have ....
Florent's team of workers have left for the moment as we are waiting on information for the sewage treatment plant before continuing so I am on site alone. I have finished the last part of ....
What a miserable day! Almost non-stop rain during the morning which flooded the site making it difficult to do the concreting of the bases for the pergola posts for the car park. In the brief ....
The only gaine (conduit) I installed without pre-wiring was the fibre optic. Issues with Orange (who manage the infrastructure in France) left me with no cable to insert. I have since bought my own to ....
With the jointing finished and the embedded bush root finally dead, we were able to cut out the exposed section, drill it and fill it with more herbicide just in case and finish off the ....
After a bit of going and frying with the windows supplier we finally have agreed sizes for the thresholds for the doors and the large fixed window. Utility door with muck ready to spread, work ....
Finally the jointing is finished. Scaffold down at the front to reveal its new face and the internal wall also cleared (although still a bit damp as it is inside). The top of the attic ....
Front wall finished today (still to be brushed off) and a start made on the internal wall. Almost there.