Skip to content
  • 10:21
  • Saturday
  • 12 July 2025
  • Home
  • Welcome
  • A New Project
  • Drawings
  • 15 Rue Sainte Benête Videos 28th march 2025
  • M-B Importation
15 rue Sainte Benête – The Development Blog

15 rue Sainte Benête – The Development Blog

Latest News
Welcome (Sticky Post)  |  
July 2  |  
July 1  |  
June 30  |  
June 28  |  
June 27  |  
Uncategorized

July 2

Full story
Master Bedroom

July 1

Full story
Uncategorized

June 30

Full story

BBQ Guttering 1

12 March 202414 March 2024 gjj

I dismantled my supports to paint them with a protective black stain prior to installing them. I used the same stain to finish off the cut sections of the timber frame. Here are before and ....

Continue reading
BBQ/Workshop, Timber Frame

Upper Mezzanine Floor 5

11 March 202414 March 2024 gjj

Started the day by trimming the joists in preparation for the oak fascia that has now been ordered but will a 4 to 6 week delivery! Experimented with the oak flooring to see how to ....

Continue reading
BBQ/Workshop, Upper Mezzanine

Upper Mezzanine Floor 4

8 March 202414 March 2024 gjj

As the oak came from the supplier with marks on it I have decided to plan and/or sand it back to fresh wood. The belt sander dealt with it quite quickly. I then installed the ....

Continue reading
Upper Mezzanine

Upper Mezzanine Floor 3

6 March 202414 March 2024 gjj

As part of the balcony installation I need to install a fascia for the bolts. As I only had one beam left I decided to cut it in half lengthways. What a job! Even cutting ....

Continue reading
BBQ/Workshop, Upper Mezzanine

Upper Mezzanine Floor 2

5 March 202414 March 2024 gjj

I need to cut some of the oak beam ends and they are heavy. Much too heavy to balance on the chop saw now it is on its stand. So, a sawhorse is required and ....

Continue reading
Upper Mezzanine

Upper Mezzanine Floor 1

4 March 202414 March 2024 gjj

Just a half day on site today and it was slow progress as I have been cutting and drilling oak beams. Only on photo of the first section of beam cut, drilled and positioned under ....

Continue reading
Upper Mezzanine

Tidying Up

1 March 20244 March 2024 gjj

Another miserable, wet day. Not an issue as I planned to work inside today. First job was a serious tidy up as I need to get the ground floor cleared and ready for the underfloor ....

Continue reading
First Floor, Timber Frame

Windows and Timber Frame Installation 21

29 February 20244 March 2024 gjj

Alain Chergui arrived first thing and delivered back the left over tiles from the floor he has just installed. The tiles are well travelled. We bought them initially for the new floor at the Chai ....

Continue reading
Timber Frame

Windows and Timber Frame Installation 20

28 February 20244 March 2024 gjj

The morning began dry and bright so I was able to work on the cladding over the smaller set of doors. I managed to install the piece on the left easily enough but the right ....

Continue reading
Timber Frame

Windows and Timber Frame Installation 19

27 February 20244 March 2024 gjj

More rain stopped me working yesterday but today it is relatively dry. I used the time yesterday to visit a metal worker to discuss the metal trays for the window cills and catch up on ....

Continue reading
Timber Frame

Posts pagination

Previous page Page 1 … Page 25 Page 26 Page 27 … Page 45 Next page

Recent Posts

  • July 2
  • July 1
  • June 30
  • June 28
  • June 27

Archives

Categories

Proudly powered by WordPress | Theme: news-box by wpthemespace.com.