January 2
First job is to paint behind the second column. First coat up and drying. While the paint dries the plasterboard is installed (uninsulated as it is the cold room). Some of the offcuts are used ....
First job is to paint behind the second column. First coat up and drying. While the paint dries the plasterboard is installed (uninsulated as it is the cold room). Some of the offcuts are used ....
Time to hit the cold store. I need to finish the preparation for the tidy up of electric cables. All a bit of a mess at the moment and after a chat with Erik when ....
Last day before Christmas. Tomorrow it is shopping and preparing for the festive break. Gave myself the whole day to install the four final ground floor circuits (including switching to the first floor). It went ....
More rearranging. Philippe continues to volunteer to help me in the house so today we moved one of the stacks of plasterboard up to the first floor and some to the upper mezzanine. Just enough ....
Kitchen Cooker Wiring for plugs, fan and the AGA plus a 6mm2 cable for the electric hob. Meanwhile to bring the AGA around from Henri's house now the wall has separated us, it is time ....
External Light to Utility Door More French spaghetti Light fitted And working
TEXT Another pipe in the wrong place! The washing machine has to go here. Problem is there is a bend at the level of the floor so a connection will not be easy for either ....