July 22
Lee has progressed well even through he is on his own. I occupied myself by building and fitting the wardrobe units for the mezzanine space. The right had sifde was a little tight but I ....
Lee has progressed well even through he is on his own. I occupied myself by building and fitting the wardrobe units for the mezzanine space. The right had sifde was a little tight but I ....
Lee is on site today and working upstairs so I am back downstairs crying on with more plaster boarding to get the switches properly installed. Spot the difference on this section of wall in the ....
It is Sunday and I have come in to do some final touches before Lee arrives next week. He has asked me to foam fill any large gaps in the boards. They will be cut ....
More plasterboard manipulation in the office area to get the boards up. I did get it finished but forgot to photograph it.
It was a long time ago I installed these switches and sorting the spaghetti of wires to reposition them from the rebate wall to the staircase wall was a bit of a challenge. I experimented ....
Although the first floor rooms are ready I also want to get the upper mezzanine prepared for jointing and painting. To do that sensibly, I need to plasterboard the wall that rises from the ground ....
Everything is now ready for Lee to come in and joint the boards with the exception of this corner in the guest bedroom. The issues with the volet over the front door has still not ....
Yesterday was spent moving the remaining items from the storage area so it could go off hire and save some money. The weather has been very kind and most of the stuff brought over is ....
With the insulation in place the cabling can be prepared. Took some time as the original design would not work with the positions of the ceiling support bars but eventually I found a spacing that ....
Into the master bedroom. First is the insulation. It is hot and sweaty and I am wearing a full face mask to avoid inhaling the dust so not a pleasant job.