January 7

7 January 202510 January 2025 gjj

Not much to show for a day’s work but these will be the ventilation pipes for the shower and utility rooms. A bit tricky getting the long pipe in through the bogging and with the ....

Continue reading
Ground Floor, Shower Room, Utility

January 6

6 January 202510 January 2025 gjj

With the cold store done (except for the ceiling) I turn my attention to the shower room. The sewage pipes are dismantled and glued back In place before getting hidden. Also found time to finally ....

Continue reading
Ground Floor, Shower Room, Utility

January 3

3 January 202510 January 2025 gjj

More plasterboarding in the cold store. The interior walls get insulated to separate the cold store from the rest of the house. Over the insulation the plasterboards are fitted. The final piece is over the ....

Continue reading
Cold Store, Ground Floor

January 2

2 January 202510 January 2025 gjj

First job is to paint behind the second column. First coat up and drying. While the paint dries the plasterboard is installed (uninsulated as it is the cold room). Some of the offcuts are used ....

Continue reading
Cold Store, Ground Floor

December 30

31 December 202410 January 2025 gjj

Time to hit the cold store. I need to finish the preparation for the tidy up of electric cables. All a bit of a mess at the moment and after a chat with Erik when ....

Continue reading
Cold Store, Ground Floor

December 28

27 December 202410 January 2025 gjj

Yesterday and today I have been wiring the upstairs circuits to the first socket or switch so that all the circuit tails are fed to the distribution board. I will finish the circuits later but ....

Continue reading
First Floor, Master Bedroom

December 23

25 December 2024 gjj

Last day before Christmas. Tomorrow it is shopping and preparing for the festive break. Gave myself the whole day to install the four final ground floor circuits (including switching to the first floor). It went ....

Continue reading
Electrics, Ground Floor, Services, Upper Mezzanine

December 19

19 December 202425 December 2024 gjj

More rearranging. Philippe continues to volunteer to help me in the house so today we moved one of the stacks of plasterboard up to the first floor and some to the upper mezzanine. Just enough ....

Continue reading
First Floor, Ground Floor, Upper Mezzanine

December 17

17 December 202425 December 2024 gjj

In preparation for the first floor electrics I ache had a big tidy up, sweep up and vacuum. It needed it. Relaid the tarpaulin and added some sheets of OSB to protect the oak floor.

Continue reading
First Floor

December 13

13 December 202425 December 2024 gjj

Completing the security lights at the back. Mystaff was not long enough at 5m so I taped it to my longest level to achieve circa 6.5m to make sure all the lights whet in at ....

Continue reading
Electrics, External

Posts navigation

Older posts
Newer posts

Recent Posts

  • August 31
  • August 24
  • August 22
  • August 21
  • August 20

Archives

Categories

Proudly powered by WordPress | Theme: news-box by wpthemespace.com.