External Slabs 4
In my continuing quest to clear the site as much as possibleI have loaded the trailer for the recycling centre. I have been installing and testing the internet system to enable me to get the ....
Views of the property from the outside
In my continuing quest to clear the site as much as possibleI have loaded the trailer for the recycling centre. I have been installing and testing the internet system to enable me to get the ....
While Metawaley got on with the slabs (with my occasional help) I got on with the small jobs around the site. First, the old ladder that Dave and Dave helped me to move was repositioned ....
Good start to the day (Not). Despite agreeing to a meeting on site this morning I got an SMS from the boss to go to Cognac and collect Metawaley (now on his own) from the ....
The tilers finally arrived at about 11.00 this morning after telling me 08.00. They made a quick start. The first thing was the completion of the jointing on the ground floor. The assistant/driver can be ....
I had cancelled the tilers because of the weather. It was partly because I did not want them laying the slabs in wet weather and partly because the weather had pushed my schedule back and ....
Emptied more shelving in the bike store and dismantled and rebuilt it in the workshop. The bike store is now clear and ready for floor slabs. Then did the same in the garden store but ....
Came in via the electrical shop having bought the bits need to get the cabling from the panels down to the underground cable that connects the BBQ/Workshop to the car park. Having read the manual, ....
I am not keen on moving the PV Panels yet again and despite chasing MG Habitat for a return to site date I have heard nothing back. So I have decided to install them on ....
Lots of site clearing in preparation for the tilers to return for the external slabs. Found time to finish the insulation of the corner of the workshop and clad it in OSB. emptied, dismantled and ....
In order to continue with the flooring upstairs I have laid the second plywood sheet for the en-suite but still need some more to trim off the end which is at an odd angle. In ....