Office Mezzanine, Paths and Enclosures
The new oak beams are laid in place and inserted into new holes in the wall before being enclosed. A stairwell space needs to be made but I can get a good idea of the ....
The new oak beams are laid in place and inserted into new holes in the wall before being enclosed. A stairwell space needs to be made but I can get a good idea of the ....
More work on the attic floor joists while externally the ground is flattened and the pathway foundation rubble laid.
With the old warped beams removed from the upper mezzanine, a support beam to level the new oak beams is placed in position. With the first floor and lower mezzanine joists in place I have ....
While the guys have been installing the kerbstones by the car park and around the house, I have got on with installing the first floor joists.
While the weather is still good, the kerbstones are laid to define the garden boundaries. Oops, this cables should have gone under the kerbs. The new garden gate and the holes for services through to ....
The concrete base has gone into the garden store. And the new replacement beam has been installed over the existing one that gave me concerns at one end. Also te high level beam is in ....
Florent's team returned to site today and immediately set about installing the missing floor beams that were recently delivered for both the first floor and attic . By the end of the day the attic ....
Day spent aligning panels and screwing them in place to secure them. Then drove around to the other side of the hameau to take a picture of the rear of the house from across the ....
With Phillipe helping again the morning was spent lifting the final roofing sheets in place together with the ridge. I then played with one of the side panels before getting bored. So in stead of ....
Back to the roof of the car park, I adjusted the rafters to align them properly then fixed the final battens. Then, with a lot of help from Phillipe across the road the large sections ....