July 24
The gravel arrives on a lorry and trailer. While I hold the cables up above the entrance archway, the bags are hoisted over the wall and positioned for their bottoms to be sliced open to ....

July 23
The well takes shape Conecting them together was a bit of a nightmare bur Florent got it done. The fosse and drainage bed is inspected by eau17 with Florent and Andrew in attendance. After approval ....

July 22
Kerbstones fitted for the limits of the entrance way for both cars and pedestrians. Erik has fitted the path lights and workshop board. I have fgot as far as I can with the gravel grids ....

July 20
TEXT The front entrance is marked out for the limits of the gravel finish. Erik the electrician is due back to fit out some of the items in the workshop so I have prepared a ....

July 19
A rodding eye for the sewage pipe and concrete bases for the pathway lights. The angled corner is completed with its pathway light As Alain and Jonathan level the paths, I follow up immediately with ....

July 18
Florent connects the fosse to the overflow well. The car park is levelled and compacted and the final kerbstones are added with a slight adjustment to the plan to allow an angled corner to aid ....

July 17
The fosse is stabilised with stone. This new design avoids a concrete base and anchoring to prevent the fosse from floating. instead the crenelated design of the sides are filled with stones and the whole ....

July 16
Another flower bed emerges outside the kitchen window. Cables will need to be tidied but not until final positions of the panels is known. The PV distribution/Control Board is prepared and the BBQ panels isolation ....

July 15
Panels and pathways take shape. My lifting system works well, even in the wind. The trickiest bit is getting the panel off the lifter and onto the roof but then it is relatively easy as ....