15 rue Sainte Benête – The Development Blog

15 rue Sainte Benête – The Development Blog

Latest News
Welcome (Sticky Post)  |  
May 19  |  
May 16  |  
May 15  |  
May 14  |  
May 10  |  

Category: External

Views of the property from the outside

Workshop Refit

31 May 202423 June 2024 gjj

The tiles and grouting are set so I have cleaned them down (many were still stained with fire damage and charcoal) and started to replace the items in the workshop. As you can see I ....

Continue reading
BBQ/Workshop

Ground Floor Tiling 12

28 May 202423 June 2024 gjj

Metawaley grouted as much as he could in the house but ran out of material and my supplier had none left so I have had to order it. He was able to finish the grouting ....

Continue reading
BBQ/Workshop, Ground Floor

Ground Floor Tiling 11

27 May 202423 June 2024 gjj

Monday morning and no translator. we use google translate and get by pretty well.Matetawaley is enamoured with Judith after the excellent dinner we had last night. The shower is built and then tiled around and ....

Continue reading
BBQ/Workshop, Ground Floor

Ground Floor Tiling 10

26 May 202423 June 2024 gjj

It is Sunday morning and the tiling continues. I turn my attention to the corner all in the workshop to develop its structure. no drawings here I am winging it off the top of my ....

Continue reading
BBQ/Workshop, Ground Floor

Ground Floor Tiling 8

24 May 202423 June 2024 gjj

It is Friday morning and I have come in just to lay the fall for the shower floor. The tiles are there to hold the pieces of wood that are protecting the sides. Once finished ....

Continue reading
BBQ/Workshop, Ground Floor

EV Charging, Travertine, Fountain and Ground Floor Tiling 6

22 May 202423 June 2024 gjj

I have finally received instructions on how to reset the Tesla charger and by following their instructions, I finally got it up and running. This records the first three phase charge using 16 Amps and ....

Continue reading
Electrics, Garden, Ground Floor

Ground Floor Tiling 3

17 May 202423 June 2024 gjj

Second day of screed mixing. Good progress but the materials are running out. Even with the extra bags of sand you can see in the driveway that were delivered this morning it will not be ....

Continue reading
BBQ/Workshop, Ground Floor

Ground Floor Tiling 2

16 May 202423 June 2024 gjj

Today the screeders arrived to lay the ground floor over the underfloor heating pipes. While they organised themselves, I finished off the installation of the earthing points in both the workshop and the car park ....

Continue reading
BBQ/Workshop, Car Park, Ground Floor

First Floor Flooring 9, EV Charger installed

15 May 202423 June 2024 gjj

A record of the position of the central point of the fibre optic cable where the rods were brought together. Now all buried and without the inspection chamber that is now redundant. On the first ....

Continue reading
Car Park, First Floor, Garden, Services

Fibre Optic Arrives. First Floor Flooring 8

14 May 202424 June 2024 gjj

The free.com engineer is due this afternoon so I spent this morning with some small issues. First, I have installed a threshold for the workshop door as there will be different tiling inside the workshop ....

Continue reading
First Floor, Garden, Services

Posts navigation

Older posts
Newer posts

Recent Posts

  • May 19
  • May 16
  • May 15
  • May 14
  • May 10

Archives

Categories

Proudly powered by WordPress | Theme: news-box by wpthemespace.com.