External Slabs 4
In my continuing quest to clear the site as much as possibleI have loaded the trailer for the recycling centre. I have been installing and testing the internet system to enable me to get the ....
Views of the property from the outside
In my continuing quest to clear the site as much as possibleI have loaded the trailer for the recycling centre. I have been installing and testing the internet system to enable me to get the ....
While Metawaley got on with the slabs (with my occasional help) I got on with the small jobs around the site. First, the old ladder that Dave and Dave helped me to move was repositioned ....
Good start to the day (Not). Despite agreeing to a meeting on site this morning I got an SMS from the boss to go to Cognac and collect Metawaley (now on his own) from the ....
The tilers finally arrived at about 11.00 this morning after telling me 08.00. They made a quick start. The first thing was the completion of the jointing on the ground floor. The assistant/driver can be ....
The finished repair of the front arch. Some changes to the kerbstones. The heat pump position had to be changed (the base was extended some time ago for it) so the pathway became too narrow ....
Despite the heavy trimming they have received, all of the fruit trees are blossoming. It was a relatively dry day so I got outside to do a list of little jobs that were outstanding. Moved ....
Before the floor can be done I need to remove the scaffolding we have been using for the upper mezzanine. However, before removing them I need to finish preparing the beams for the oak flooring. ....
I have finished cabling the panels on the car park roof and today the underfloor heating pipe is finally on site. All 500m of it. Should have been done before they fitted the heat pump ....
Both sides of the roof are now extended and recovered. Rear of the house from the fence line.
Finished off the timber framing of the workshop including the second window opening. Both verticals and horizontals for the eventual cladding. extending the sides of the roof for the PV panels. In between other work ....