May 31
Closing out some fiddly jobs while waiting for an IKEA delivery. Internal walls of the cupboard space on the mezzanine walkway prepared and used as storage for the first floor ceiling insulation. IKEA delivery arrived ....
Closing out some fiddly jobs while waiting for an IKEA delivery. Internal walls of the cupboard space on the mezzanine walkway prepared and used as storage for the first floor ceiling insulation. IKEA delivery arrived ....
I need to design a support system in the wall before closing it off to ensure the towel rail does not get pulled off just plasterboard. So I have inserted a structure but not yet ....
The Master Bedroom is still to be finished but with the delivery of the hydro boards I have turned my attention to the two en-suites. After completing the wiring and the insulation, the boards can ....
Before installing the plasterboard I need to check all the wiring is in. Here I have temporarily hung the lights over the mezzanine walkway and one lamp for the office mezzanine.
Vapour barrier and plasterboard in the dressing room. I have repositioned the shutter controls to inside the rebate for the window as it is more convenient than on the outer wall as in this room, ....
With the plasterboard pile renewed I can get on with the upstairs. Here in the dressing room I have insulated and prepared the tapes to support the vapour barrier Likewise in the Master en suite ....
Internal Walls in the Dressing Room are finished. External wall still to be done but the radiator is now fitted but not connected. It needs to come off for me to prepare and paint the ....
The car went for a service this morning so time on site was limited. However I managed to get the electrical points and (future wardrobe) light points in to the Dressing Room. The corner will ....
The Master bedroom radiators finally installed and tested. I cannot test the Guest Bedroom yet as the circuit includes the towel rail in the bathroom that is not fitted so I have ordered some blanking ....
Time to start the external wall cladding upstairs. This is the dressing room, insulated then sealed with a vapour barrier before plasterboarding. A late design change as a water tap is now required for the ....