Skip to content
  • 01:01
  • Saturday
  • 5 July 2025
  • Home
  • Welcome
  • A New Project
  • Drawings
  • 15 Rue Sainte Benête Videos 28th march 2025
  • M-B Importation
15 rue Sainte Benête – The Development Blog

15 rue Sainte Benête – The Development Blog

Latest News
Welcome (Sticky Post)  |  
July 2  |  
July 1  |  
June 30  |  
June 28  |  
June 27  |  
Uncategorized

July 2

Full story
Master Bedroom

July 1

Full story
Uncategorized

June 30

Full story

July 12

12 July 202426 December 2024 gjj

Florent's first action is to topcoat and level the paths with crushed stone. I get my first delivery of the metal rail system that will form the interior walls, placed by the insulation for easy ....

Continue reading
Uncategorized

July 11

11 July 202426 December 2024 gjj

Florent arrives on site and the piles of stone are finally cleared. Large formations stones from old farm buildings that have been excavated during the works are moved (by me) to the storage area. More ....

Continue reading
Uncategorized

July 9

9 July 202426 December 2024 gjj

The small lawn in front of the BBQ is finally cleared up to the top end storage area. The rear of the house is also cleared with items returned into the garden store (I will ....

Continue reading
Uncategorized

July 8

8 July 202426 December 2024 gjj

The sewage fosse arrives! It is a lot bigger than it looks in the pictures. Main chamber on the right and the overflow liquid chamber on the right. An internal pump aerates the liquids and ....

Continue reading
Uncategorized

July 5

5 July 202426 December 2024 gjj

Back to the PV panels while the sun shines. Up the ladder for a quick check on dimensions and I intend trying the plasterboard lifter to get the panels up on to the roof rather ....

Continue reading
Uncategorized

General Tidy Up

2 July 202415 August 2024 gjj

Tidying up the site after the tilers have gone. Flower pots appear on the patio and more washing down of the slabs. Last of the big pots moved. Cladding wood moved and stored in the ....

Continue reading
Uncategorized

July 1

1 July 202415 August 2024 gjj

Grouting finished, Metawaley stands back and admires his work while I start the big sweep and wash. Will need to be done several times over the next few days. And find some time to do ....

Continue reading
Uncategorized

External Slabs 7

30 June 202415 August 2024 gjj

It's Sunday and I am back again as the tilers insist on working the weekend and I want to oversee what they are doing. Front patio BBQ/Workshop (almost finished) Front bike store. Preparing the rear ....

Continue reading
BBQ/Workshop, Bike Store, External, Garden Store

PV Panels 11

29 June 202415 August 2024 gjj

While the slabs continued to be laid I turned my attention to wiring the PV panels control unit. The blue and white wires connect to sensors around each cable that reads the current and gives ....

Continue reading
External

External Slabs 5

28 June 202429 June 2024 gjj

Friday was a complex day. I started by driving via Cognac to collect Metawaley and bring him here to start working. Then off to Saintes for another length of cable to connect the PV controller ....

Continue reading
BBQ/Workshop, External

Posts pagination

Previous page Page 1 … Page 17 Page 18 Page 19 … Page 45 Next page

Recent Posts

  • July 2
  • July 1
  • June 30
  • June 28
  • June 27

Archives

Categories

Proudly powered by WordPress | Theme: news-box by wpthemespace.com.