Internal Electrics
It does not looks much but it took most of the day to fit the 16mm cabling in the distribution board then make the final connection at the temporary supply. 16mm is difficult to work ....
Views of the property from the outside
It does not looks much but it took most of the day to fit the 16mm cabling in the distribution board then make the final connection at the temporary supply. 16mm is difficult to work ....
Sitting happily at home catching up with paperwork I got an urgent call from my neighbor Andrew. Apparently a lorry had arrived from Estonia with no notice containing our timber cladding of charred and oiled ....
Excellent weather for opening the doors and tidying up the interior before offloading the latest timber delivery. Florent has once again organised the purchase and lent me his lorry to bring it to site. Esteban ....
After our trip to the UK I am finally back on site to see that in my absence Florent has been back to install the internet fibre box connection through the wall and in a ....
A little worrying as we are off to the UK next week and the site is now flooding. The ditch at the back of the property has overflowed into the garden preventing any further work. ....
With the water continuing to fall, Florent has only been able to tidy up the paths and fencing areas and has now left site until the sewage approval is received. timing is OK as we ....
The weather is turning very wet so I am pleased the fencing is now secured and looking good. I am waiting on approval for the sewage (assainissement) system before it can be installed so work ....
Dancing posts and gate cemented in. Lead flashing on storage roofs and the final joists are fitted.
The new oak beams are laid in place and inserted into new holes in the wall before being enclosed. A stairwell space needs to be made but I can get a good idea of the ....
More work on the attic floor joists while externally the ground is flattened and the pathway foundation rubble laid.