Author: gjj
July 30
I have organised to import 40 tonnes of topsoil to give a shallow cover over the existing earth and to fill the flower beds I have had to mark out the contours of the flower ....
July 29
Time to start the internal wall structures and tidy the workshop now that it is electrified only to find another visitor in the rear store that has got stuck in a bucket. I took it ....
July 24
The gravel arrives on a lorry and trailer. While I hold the cables up above the entrance archway, the bags are hoisted over the wall and positioned for their bottoms to be sliced open to ....
July 23
The well takes shape Conecting them together was a bit of a nightmare bur Florent got it done. The fosse and drainage bed is inspected by eau17 with Florent and Andrew in attendance. After approval ....
July 22
Kerbstones fitted for the limits of the entrance way for both cars and pedestrians. Erik has fitted the path lights and workshop board. I have fgot as far as I can with the gravel grids ....
July 20
TEXT The front entrance is marked out for the limits of the gravel finish. Erik the electrician is due back to fit out some of the items in the workshop so I have prepared a ....
July 19
A rodding eye for the sewage pipe and concrete bases for the pathway lights. The angled corner is completed with its pathway light As Alain and Jonathan level the paths, I follow up immediately with ....