April 22
Although we did work on Good Friday (as it is not a bank holiday here in France) it was agreed to take a break for the rest of Easter. The stone reveals on the original ....
Although we did work on Good Friday (as it is not a bank holiday here in France) it was agreed to take a break for the rest of Easter. The stone reveals on the original ....
Lee and Jacque arrive to start the plasterboard jointing. They assure us we will not see the joints after they have finished. They are incredibly quick and accurate with their work and the first coat ....
The final preparation required the floors to be swept, hoovered and washed to lift the dust. Only then was I able to safely tape a protective cover over the travertine (which is highly absorbent and ....
With the preparation done I was able to quickly finish the kitchen reveal. The front door reveal was larger but much easier (as it was in my wooden frame) so I had time left to ....
Another day, another delivery. Loaded last night for delivery today. I brought the van so I could fit the parasol in without dismantling it. Back on to the final reveals. Two to go and the ....
Still trying to finish off the plasterboard downstairs before the plasterers come. This is the first of the kitchen windows completed.