First Floor Flooring 3
In order to install the final heating loop I have had to take down the scaffolding that has been there for ever it seems. The ground floor is now clear. As I explained earlier the ....
In order to install the final heating loop I have had to take down the scaffolding that has been there for ever it seems. The ground floor is now clear. As I explained earlier the ....
Spot the difference? I have actually made some progress with the oak flooring on the first floor.
While my two assistants watched on, I rearranged the main staircase components, moving them from the first floor to the upper mezzanine. I also sorted the various lengths of parquet ready for the next few ....
So, with the upper mezzanine done I have moved to the lower mezzanine which is also the first floor and made a start on the oak flooring. I have had to jigsaw the boarding around ....
Another miserable, wet day. Not an issue as I planned to work inside today. First job was a serious tidy up as I need to get the ground floor cleared and ready for the underfloor ....
This morning I finished off the plywood cladding and then applied the breather paper to the upper section. I then spent the afternoon finishing the fitting the battens in preparation for the cladding. The right ....
to maintain the flooring for the window installation I had to lift the temporary floor I had fitted (22mm) that is the attic floor and replace it with thinner (12mm) boarding that is destined for ....
Dancing posts and gate cemented in. Lead flashing on storage roofs and the final joists are fitted.
More work on the attic floor joists while externally the ground is flattened and the pathway foundation rubble laid.
With the old warped beams removed from the upper mezzanine, a support beam to level the new oak beams is placed in position. With the first floor and lower mezzanine joists in place I have ....