Car Park 6
The fourth post and cross members go up. All seemed to fit well at this end including the bracing post. The other end was a different story. First the cross member was badly warped and ....
The fourth post and cross members go up. All seemed to fit well at this end including the bracing post. The other end was a different story. First the cross member was badly warped and ....
Before I could continue with the pergola I needed to sort the components into various piles so I could access them easily as needed The first job was to see if my lifting method would ....
Took me most of the day drilling the bottom of the 6 wooden posts and fitting the other half of the feet so that the posts could be installed to the bases. I laid the ....
To start the day I finished off the few remaining noggins for the mid section of the attic floor before turning my attention to the car park pergola. The concrete pads were not in quite ....
What a miserable day! Almost non-stop rain during the morning which flooded the site making it difficult to do the concreting of the bases for the pergola posts for the car park. In the brief ....
As part of clearing the car parking I have had to move all the PV panels, not just those for the BBQ area. Discovered a second one damaged unfortunately so that will also need replacing. ....
Good progress on the windows that are now nearly all concreted. One more to go. A new external office by the caravan.
Quiet day on my own on site today. Finally finished off the ivy on the walls behind the car parking area and down the wall on the roadside between the parking area and the arch. ....
When I left last night the wall had progressed well and this morning it looks good having dried out. They are doing a good job matching the existing stonework and I am sure that Henri ....
After pouring the concrete for the lintel above the door, the team got back to floor preparation laying the reinforcing bar for the concrete pour. We wanted to organise it for this week but the ....