Category: Uncategorized

July 23
The well takes shape Conecting them together was a bit of a nightmare bur Florent got it done. The fosse and drainage bed is inspected by eau17 with Florent and Andrew in attendance. After approval ....

July 22
Kerbstones fitted for the limits of the entrance way for both cars and pedestrians. Erik has fitted the path lights and workshop board. I have fgot as far as I can with the gravel grids ....

July 20
TEXT The front entrance is marked out for the limits of the gravel finish. Erik the electrician is due back to fit out some of the items in the workshop so I have prepared a ....

July 19
A rodding eye for the sewage pipe and concrete bases for the pathway lights. The angled corner is completed with its pathway light As Alain and Jonathan level the paths, I follow up immediately with ....

July 18
Florent connects the fosse to the overflow well. The car park is levelled and compacted and the final kerbstones are added with a slight adjustment to the plan to allow an angled corner to aid ....