Underfloor Heating 1
Before the floor can be done I need to remove the scaffolding we have been using for the upper mezzanine. However, before removing them I need to finish preparing the beams for the oak flooring. ....
Before the floor can be done I need to remove the scaffolding we have been using for the upper mezzanine. However, before removing them I need to finish preparing the beams for the oak flooring. ....
This morning I finished off the plywood cladding and then applied the breather paper to the upper section. I then spent the afternoon finishing the fitting the battens in preparation for the cladding. The right ....
It does not looks much but it took most of the day to fit the 16mm cabling in the distribution board then make the final connection at the temporary supply. 16mm is difficult to work ....
Excellent weather for opening the doors and tidying up the interior before offloading the latest timber delivery. Florent has once again organised the purchase and lent me his lorry to bring it to site. Esteban ....
It does not look much but the beams over the doors are installed and insulated and we have progressed the enclosure for the shutter over the smaller door. I also started installing the breather membrane ....
A combination of lots of issues including weather, lack of approval and my back has kept me at home planning for some time but today I am on site again for the first time since ....
The concrete base has gone into the garden store. And the new replacement beam has been installed over the existing one that gave me concerns at one end. Also te high level beam is in ....
Florent's team returned to site today and immediately set about installing the missing floor beams that were recently delivered for both the first floor and attic . By the end of the day the attic ....
Finally the jointing is finished. Scaffold down at the front to reveal its new face and the internal wall also cleared (although still a bit damp as it is inside). The top of the attic ....
Front wall finished today (still to be brushed off) and a start made on the internal wall. Almost there.