July 15
Panels and pathways take shape.


My lifting system works well, even in the wind. The trickiest bit is getting the panel off the lifter and onto the roof but then it is relatively easy as long as I can avoid tripping up on cables and supports.




The garden levelling begins. Space is cleared and levelled for the caravan and the flower beds are dug out to receive some topsoils.


Flower bed shapes are to Jude’s instructions. Some final edging is fitted and the crushed stone added.



The filter bed for the sewage drainage is prepared.

The caravan is finally moved to its new location.

The hydrangea is planted and under the compressor is filled to receive shingle.



Meanwhile I continue with the PV panels and finish off the car park roof.