July 12

Florent’s first action is to topcoat and level the paths with crushed stone.

I get my first delivery of the metal rail system that will form the interior walls, placed by the insulation for easy access. A quick play with a Rail (one at top and one at bottom) and a Montant to understand how the system works as I have never used it before.

Back to the PV panels on the car park. The micro-inverters (ondulateurs) are installed and cabled and the cable connected to the isolation switch. First line of panels are fitted and adjusted to be centralised on the roof.